捆绑SM社区

New Vic Concept

InfoConstruction

Keeping communities informed.听Minimizing disruptions.听Protecting teaching and research integrity.

捆绑SM社区

Road closure calendar

This table indicates the on-going work of the Soci茅t茅 qu茅b茅coise des infrastructures (SQI), Ville de Montreal, 捆绑SM社区/The New Vic Project/ Facilities Management and Ancillary Services (FMAS) and the Ville de Montr茅al.

DATES MANAGED BY STREET NAMES TYPE OF CLOSURE NOTES

November 4 to December 20, 2024

and

January 6 to February 21, 2025

捆绑SM社区/New Vic Des Pins, between University and Docteur-Penfield Closed to all road traffic

New Vic Project. Detours will direct drivers towards Sherbrooke. Services should not be affected.

Notice of works and detour map

January 2025 SQI Des Pins, between Docteur-Penfield and MacTavish Partial closure SQI project. Detours will direct drivers towards Sherbrooke. Services should not be affected.
January 13 -24, 2025 SQI University Partial closure

SQI project. Services should not be affected.

Notice of works

(Last update:听 December 18, 2024)

Looking for more information on road closures around the larger Montreal area? Visit the .

Plans and progress

Work underway

  • Decontamination of pavilions A, E, M and S (See "Plans" below.)
  • Structural decoupling of renovated and deconstructed pavilions
  • Recovery of Queenston stone in pavilion S
  • Recovery of windows (glass, steel, concrete)

Plans

捆绑SM社区 Pavilions - Aerial View
捆绑SM社区 Pavilions - Aerial View

Worksite Plan
Worksite Plan

Worksite Plan - 捆绑SM社区 Pavilions
Worksite Plan - 捆绑SM社区 Pavilions

Nettoyage post-d茅samiantage
Post-asbestos removal cleaning

D茅solidarisation entre le pavillon L et l鈥檃nnexe du pavillon L
Decoupling of Pavilion L from Pavilion L annex

Mobilisation des 茅quipements
Mobilization of equipment in preparation for recovery of Queenston stone in pavilion S

The next 6 months

  • Continuation and completion of decontamination work inside pavilions A, E, M and S听(See "Plans" above.)
  • Deconstruction of pavilion L annex
  • Continued recovery of Queenston stone on the west facade of pavilion S
  • Installation of support structure for footbridge (between pavilion S and The Neuro)
  • Start of deconstruction work on pavilions M and S:
    • Removal of windows
    • Removal of mechanical equipment from roofs
    • Removal of roof membranes
    • Selective deconstruction at pavilions M and S
  • Street cuts (obstructions on University Street and Avenue des Pins)
  • Removal of a gas tank

Community impact mitigation measures

Noise

Noise-generating work will be carried out in accordance with current municipal regulations:

  • Monday to Friday: 7 a.m. to 7 p.m.
  • Saturday: 7 a.m. to 7 p.m. (when required)
  • Sunday: No work

Vibration

  • Vibration limitations have been imposed on contractors. Their work methods will be adapted to comply with these limits.
  • Installation of 27 seismographs for continuous vibration monitoring.
  • Seismographs will be added around the site (south side of Avenue des Pins, east side of University Street).
  • Establishment of a threshold to be respected for highly sensitive buildings: historic and protected structures or already deteriorated structures.

Dust

  • Street cleaning with mechanical broom
  • Use of water to suppress dust during deconstruction of concrete structures

Latest news

News regarding work progress will be published here.

Contact information

New Vic Project Office
772 Sherbrooke Street West, 2nd听floor
Montreal, Quebec H3A 1G1

Email:听new.vic [at] mcgill.ca

捆绑SM社区 is on land which has long served and continues to serve as a site of meeting and exchange amongst Indigenous peoples, including the Haudenosaunee and Anishinabeg nations. We acknowledge and thank the diverse Indigenous peoples whose presence and contribution mark this territory on which peoples of the world now gather.

Back to top