News
Construction Start: MNI - Cyclotron
Published: 17 May 2023
捆绑SM社区 has mandated ARDEC to carry out the following project: Montreal Neurological Institute / 18-121 - Cyclotron.
The project consists of replacing the cyclotron's conduit.
Project manager:聽Eric Boutet, CIMA+ -聽eric.boutet [at] cima.ca
Assistant project manager:聽Aldo Aranza Mendoza, CIMA+ -聽aldo.aranzamendoza [at] cima.ca
Construction start:聽May 19, 2023
Planned construction end date:聽May 29, 2023
Work schedule:聽Monday to Friday, 7 a.m. to 3 p.m.
Scope of work:
The work is on the exterior of the building and includes the installation of a conduit on the roof of the MNI building.
Impact:
There will be no impact on the building users, however, a crane will be used on May 19th.聽